News:

Updated interior renderings with finishes.

See Design Documents.

​

Status:

Building permit has been issued.

​

Questions?

Contact Community Center Building Committee, or

Matthew Bachtold, Library Director,  508-529-6272.

​

Project Description:

The Upton Community Center is a new facility of 15,132 square feet to house the Upton Town Library and the Council on Aging, at an estimated project cost of $12.4 million.

Located at 9 Milford Street, the facility includes a redesigned playground and shared parking with the adjacent VFW.

​

Approved by Upton Voters:

Town Meeting  5/8/2021

Town Election  5/11/2021

Interior Foundations

Mar 8, 2022

Foundations for interior support columns and walls are being poured, and more fill is being brought in to fill in the interior and bring the floor of the building up to the correct grade.

Warm weather is allowing quick progress!

2022.3.8 Great Room.jpg

Mar 8, filling the interior foundations of the Great Room.

2022.3.8 NW Corner.jpg

Mar 8, Smoothing and filling on the West side along Centerbrook

2022.3.3 Grease Trap.jpg

Mar 3, installing the grease trap for the kitchen at the northwest corner.