A new facility funded by the Town of Upton, located at 9 Milford Street
Library Open
starting May 2nd
9 Milford Street
Tues, Weds, Thurs 9am - 8pm
Fri, Sat 9am-4pm
News:
Updated interior renderings with finishes.
​
Status:
Building permit has been issued.
​
Questions?
Contact Community Center Building Committee, or
Matthew Bachtold, Library Director, 508-529-6272.
​
Project Description:
The Upton Community Center is a new facility of 15,132 square feet to house the Upton Town Library and the Council on Aging, at an estimated project cost of $12.4 million.
Located at 9 Milford Street, the facility includes a redesigned playground and shared parking with the adjacent VFW.
​
Approved by Upton Voters:
Town Meeting 5/8/2021
Town Election 5/11/2021
Roof Framing
July 26, 2022
Roof framing and plywood are being installed to create the roof of the building.
The mezzanine subfloor for mechanical equipment and storage is built over the east side, above the office spaces.
​
In the background, the playground area is being leveled and sloped.
July 17, partially installed mezzanine subfloor and roof peaks over the great room and main entrance.
July 17, on the right of photo, south end of site, the playround and slope down to nature play area are being excavated.
July 17, view directly down showing the mezzanine subfloor and roof slope on the back (west) side of the building.
July 17, view of roof and interior framing looking south along the building from the Milford street side.