Upton Town Library
Community Center Construction
A new facility funded by the Town of Upton, located at 9 Milford Street
Library Open
starting May 2nd
9 Milford Street
Tues, Weds, Thurs 9am - 8pm
Fri, Sat 9am-4pm
News:
Target Date for Opening: March / April 2023
​
Status:
Exterior finishes complete, Sidewalks and patios installed.
​
Questions?
Contact Community Center Building Committee, or
Matthew Bachtold, Library Director, 508-529-6272.
​
Project Description:
The Upton Community Center is a new facility of 15,132 square feet to house the Upton Town Library and the Council on Aging, at an estimated project cost of $12.4 million.
Located at 9 Milford Street, the facility includes a redesigned playground and shared parking with the adjacent VFW.
​
Approved by Upton Voters:
Town Meeting 5/8/2021
Town Election 5/11/2021
Sidewalks
Oct 22, 2022
Siding is being installed on the building exterior, and the concrete sidewalks have been poured and brushed.
Inside, the electrical and plumbing rough work is nearly complete, and the installation of drywall has begun.
Oct 21, Freshly poured concrete sidewalk along the back (west) side of the building.
Oct 22, Patio area at the south west corner of the building. The playground is to the right and children's library directly ahead.
Oct 22, Sidewalk along the south east corner. Future side of three accessible parking spaces.
Oct 22, Boulder scramble and one of the embankment slides leading down from the upper to lower playground areas.