Community Center Construction
A new facility funded by the Town of Upton, located at 9 Milford Street
Library Open
starting May 2nd
9 Milford Street
Tues, Weds, Thurs 9am - 8pm
Fri, Sat 9am-4pm
News:
Updated interior renderings with finishes.
​
Status:
Building permit has been issued.
​
Questions?
Contact Community Center Building Committee, or
Matthew Bachtold, Library Director, 508-529-6272.
​
Project Description:
The Upton Community Center is a new facility of 15,132 square feet to house the Upton Town Library and the Council on Aging, at an estimated project cost of $12.4 million.
Located at 9 Milford Street, the facility includes a redesigned playground and shared parking with the adjacent VFW.
​
Approved by Upton Voters:
Town Meeting 5/8/2021
Town Election 5/11/2021
Floor Slab concrete pour
Apr 18, 2022
After a rain delay, the concrete floor slab was poured on Monday, April 18.
23 trucks of concrete were delivered between 6am and 9am and the rest of the day was spent finishing the floor.
Video of the process was taken by Mark Herd, Upton resident.
Apr 18, Video of slab pouring.
Apr 16, aerial view of moisture barrier and concrete grid.
Apr 18, pouring and finishing completed.
Apr 19, dried floor slab.